Sevina Park Villas Road Development is 96% Completed
三月 1, 2021
Construction works are well underway for Cebu Exchange, with structural, architectural, and interior fit-out works ongoing. As of December 2019, project construction is at 52% completion. The project is on-schedule for the following milestones in 2020: Structural top-off on April 2020 and Phase 1 turnover on September 2020.